BSEE - Building Services and Environmental Engineer
Eaton wins Liverpool contract
Published:  20 April, 2006

The ability to meet a tight 10-week delivery schedule has won Eaton the contract to supply a 5MVA packaged substation for Liverpool’s new £70 million Met Quarter retail development.

The Met Quarter is one of many ambitious developments going ahead in the run-up to Liverpool’s reign as European Capital of Culture for 2008. The former Post Office building in the heart of the city has been redeveloped to offer 81,000 sq ft of retail accommodation for names such as Armani and Flannels together with restaurants and bars. The development by Milligan RRI, the specialist retail developer, retains the traditional façade of the old Post Office but blends this with a contemporary curved glass façade on other frontages. Internally it is designed as a three-storey covered streets mall.

A&B Engineering was responsible for installing the full electrical and mechanical services package including all landlord’s infrastructure and services mains, sub-mains, power, lighting, emergency lighting, fire alarms, sprinkler systems, security systems and data networks. Electrical installations included an 11kV substation feeding Eaton’s double-ended packaged substation at Level 4, and low voltage distribution to the individual retail units.

The 12.4m long substation had to be lowered into position by crane in sections through a 2.3m x 1.7m aperture in the switchroom roof. The substation was delivered on schedule and craned into position. The transformer housings were built at Eaton’s Birmingham factory and then flat-packed for delivery to site. The switchboard comprising ten sections, including two incoming sections, each 2.6m high by 1100mm wide by 1200mm deep was also built in Birmingham.

A & B Engineering has used Eaton equipment previously on numerous contracts including the Linda McCartney Cancer Research Centre and the Swallow Hotel in Liverpool. “We selected Eaton for the Met Quarter substation because of its competitive pricing and its ability to meet the ten-week delivery deadline” says A & B Director, Joe Carroll.

Main contractor for the Met Quarter was Carillion Building, and Consulting Engineer was Waterman Gore of Manchester.


Poll

There is an obvious need for the industry to be more energy efficient and pay more attention to the ways in which energy is both used and wasted. Do you think we have the products on the market to meet our needs?

  • Yes
  • We're getting there
  • We're a long way off
  • No
© Copyright 2008 Building Services & Environmental Engineer. Datateam Publishing Ltd. All rights reserved.
Registered in England No: 1771113. VAT No: 834 8567 90.
Registered Office: 8 Baker Street, London W1U 3LL. U.K.
Webmaster