Whilst specialists in aspects of building services
engineering may not need to be fully conversant
with The Construction (Design and Management)
Regulations (CDM Regulations) it is helpful to be
aware of the new issues relating to the framework of
Health and Safety Regulations relevant to construction projects.
For this reason, an overview of the current position is set out
below.
The CDM Regulations are 10 years old and now the Health and
Safety Commission (HSC) is half way through its four month
consultation on its proposals to revise and consolidate the CDM
Regulations and the Construction (Health, Safety and Welfare)
Regulations 1996 (CHSW Regulations) and revise supporting
guidance.
Background
In 2002 the construction Discussion Document (DD) formally
recognised that all was not as hoped in the industrys health and
safety performance. Discussions at this stage have led to the
conclusion that for the main part the principles underpinning the
CDM Regulations were accepted. However, the methods adopted
to implement the CDM Regulations often resulted in the principles
being obscured beneath layers of bureaucracy and paperwork.
Given this, the HSC concluded that the CDM Regulations were in
need of revision by refocusing attention on effective, but practical,
planning and management of construction projects. The HSC
produced a consultation paper explaining the proposed changes on
31 March 2005 with the consultation open until 29 July 2005. A
draft set of amended CDM Regulations is included together with a
draft of revisions to the Approved Code of Practice. The HSC
considers it has:
Simplified and clarified the CDM Regulations allowing duty
holders to know what is expected of them.
Focused on planning and management and not the plan and
other paperwork to ensure that paperwork and bureaucracy is
minimised.
Maximised their flexibility so that they will work with the mix of
contractual arrangements.
Strengthened requirements of co-ordination and co-operation
especially between designers and contractors so to improve
integration.
Simplified the assessment of an organisations competence.
These new regulations will apply to all notifiable projects in Great
Britain and are intended to achieve the objectives outlined above
whilst maintaining the underlying principles of the existing CDM
Regulations.
Key changes
In summary the proposed key changes to the CDM Regulations
include:
Application and notification there will be only two types of
construction projects notifiable and non notifiable. All
requirements will apply to notifiable projects whilst
requirements relating to appointments, plans and other
paperwork will not apply to non notifiable projects.
Clients - must now ensure project management arrangements
are made for health and safety by exercising their influence and
control taking into account those who will construct, maintain
and demolish the structure.
Agents - the provisions on agents will be removed as they are
seen as allowing clients to absolve themselves of their legal
obligations. Several clients on the same project can now agree
amongst themselves that one client should be the sole client.
The aim is to prevent anyone retaining control whilst avoiding
responsibility.
Planning Supervisor - the role of planning supervisor will be
abolished and replaced with a co-ordinator who advises the
client. Clients must ensure that the co-ordinator.
performs its duties; and
is appointed before design work starts.
Designers must eliminate hazards where possible and reduce
any remaining risks. Their duties are extended to ensure that
fixed work places (offices, shops and factories) are safe to use.
Principal Contractor - must now ensure that the construction
phase is managed to ensure completion of the project safely
and without risk to health. There can now be only one principal
contractor on a project.
Mobilisation:
Clients must now ensure there are sufficient resources
(including time) which are suitable to ensure that work can
be carried out without risk to health and safety.
Co-ordinators must inform principal contractors/
contractors that they are appointed and of the minimum
notice they are allowed between appointment and the
commencement of work to prepare for construction of the
work.
Clients and principal contractors must ensure that
specified welfare facilities are in place at the start of
construction.
Pre-tender or pre-construction plan this will be replaced by
an information pack that should focus attention on
communication of the information that designers and
contractors need to plan and do their work.
Health and safety file this will be required for a site rather
than for each particular project.
Demolition must be planned and carried out in such a
manner as to prevent, so far as is practicable, danger and that
arrangements for demolition work must be recorded in writing.
Civil liability - employees (but not self-employed workers) will
now be permitted to take action in the civil courts for injuries
resulting from failure to comply with duties under the
Regulations.
With the consultation open until 29 July 2005, the HSE hopes to
have the new regulations and guidance in place by October 2006.
An update will be provided when the consultation has closed. If the
HSE is to achieve this, then it will have a very busy summer!
About George Davies Solicitors
George Davies Solicitors are based in Manchester City Centre.
They specialise in all aspects of law for both companies and
private individuals and boast a substantial property
department within which sits a niche construction team with
experience in a full spectrum of construction law services. The
Head of Construction, Catherine Kay can be contacted on 0161
234 8861 or emailed at catherinekay@georgedavies.co.uk




