The Hazlitt Theatre in Maidstone, Kent, presents an eclectic mix of entertainment for all the family. However it was decided that certain aspects of the theatre required updating.

PF116

The existing inefficient plant was replaced with Mikrofill equipment and housed in a newly constructed rooftop plantroom.

 

The new mechanical equipment was specified by expert consulting engineers, Mervyn Hayes Associates, on behalf of Maidstone Council. Three Ethos 130kW stainless steel, wall mounted condensing boilers with a combined turndown ratio of 21>1, were installed by mechanical contractors, Hadene Building Services of Chatham, Kent.

 

The boilers are mounted on specially fabricated frames paired with the Mikrovent 400 low loss header/air and dirt separator and pressurised by a Mikrofill 500 package.

 

The new plantroom offers unparalleled efficiency as well as allowing valuable space for service and maintenance.

 